# Settlement would let Xcel recover Hayden Unit 2 repair costs from customers
- URL: https://yvindy.com/hayden-unit-2-repair-xcel-settlement/
- Published: 2026-11-27T20:58:13.000Z
- Updated: 2026-11-27T20:58:13.000Z
- Description: Xcel put the scrubber repair at about $9 million to $10 million in June, for a coal unit scheduled to retire in 2027. Regulators aim to rule before Dec. 31.
- Author: Anna Parashina
- Tags: Government, Hayden

Colorado utility regulators are weighing a settlement that would let Xcel Energy recover the cost of repairing a scrubber at Hayden Station’s Unit 2 through an existing cost-recovery mechanism. Xcel would earn no return on it.

The settlement covers how Public Service Company of Colorado, Xcel’s Colorado utility, plans to line up enough power supply for 2027 and 2028\. Its lead item keeps another coal unit, Comanche Unit 2, running through Dec. 31, 2027\. The Hayden repair is one of five “Other Measures” listed beneath it.

The commission’s trial staff, the Colorado Energy Office and the state’s Utility Consumer Advocate are among the parties that signed it, and no party opposes it. The commission has set a goal of ruling before Dec. 31.

## The broken scrubber

Unit 2 “went offline in late 2025 and returned to service in April with a capacity derate of approximately 25%,” Zeryai Hagos said in written testimony filed June 15\. Hagos, a regional vice president for integrated system planning at Xcel Energy Services, said “the cause of the derate is due to equipment issues.”

Michael V. Pascucci, Public Service’s regional vice president for regulatory planning and policy, testified the same day that the company had “begun the process to fully repair the scrubber at Unit 2.” He said Xcel expected the unit to return fully to service in August 2026.

Xcel’s Nov. 20 list of tight-supply days shows Unit 2 as derated on Aug. 11\. The last day on that list, Aug. 20, names neither Hayden unit. The exhibit doesn’t say whether the repair is finished. Is the work done, and when did Unit 2 return to full capacity?

Hagos testified that Hayden’s other owners, PacifiCorp and Salt River Project, “are not interested in funding the necessary repair.” For its analysis, he said, Xcel “assumes that it bears the full cost of the restoration and receives the full capacity benefit.”

Pascucci said Xcel was still working with the co-owners in June on a contract for the restored capacity. Under the plant’s participation agreement, every owner must consent before “certain large capital expenditures at the plant, including the scrubber repair,” he said. A commission finding that the repair is reasonable “can provide the Hayden Participants with additional confidence in moving ahead,” he added. Have the co-owners consented, and is a capacity contract signed?

## Recovering the cost

In June, Pascucci put the repair at about $9 million to $10 million. He said that matched the estimate in Xcel’s April 15 report. What has the repair cost so far, and will it pass $10 million?

Xcel says the repair restores capacity at relatively low cost, and Pascucci called it cost effective compared with other options. Hagos testified that a full restoration “will result in 64 MW of incremental nameplate capacity with a high accreditation and a relatively low cost compared to other RA Actions.”

Xcel first proposed recovering the cost through its Electric Commodity Adjustment. The settlement moves it to the company’s Purchased Capacity Cost Adjustment, or PCCA. There, Xcel may recover the cost “as an expense without an attendant rate of return or carrying cost,” subject to a later prudence review. If the costs are under $10 million, Xcel would recover them over six months. Above $10 million, recovery would stretch over 12 months. The settlement sets no ceiling on the cost and creates no presumption that the amount spent was prudent.

Pascucci testified that expensing the repair, instead of recording it as a capital addition recovered in a later rate case, means “forgoing a return on the costs, which reduces the cost to customers.” He said Xcel chose that route “given the short remaining life of the unit and benefit to customers.” Trial staff noted that the repair is proposed to be treated as an operating expense instead of a capital cost.

Erin T. O’Neill, the commission’s deputy director of fixed utilities, testified for its trial staff, which signed the settlement. She said Xcel would recover the settlement’s costs as they are incurred, and parties could challenge them later in an annual prudence review. She wrote: “So for instance, the Company would have a presumption of prudence that the repair of Hayden Unit 2 is a reasonable action to take but parties may challenge the costs incurred for actually conducting the repairs.”

The cost would be recovered from Xcel’s Colorado electric customers. The records don’t say whether any Routt County homes or businesses are Xcel electric customers. Does Xcel serve any electric customers in Routt County? Neither the Town of Hayden nor Routt County is a party to the case.

## Retirement dates

Pascucci testified that “Hayden Unit 2 is scheduled to retire in 2027” and Unit 1 in 2028, under a 2022 commission decision that moved up coal retirements. He described the work as “a repair to a unit with limited remaining useful life but significant near-term benefits.”

The settlement doesn’t change Hayden’s retirement dates. Comanche Unit 2, which the settlement keeps running through 2027, “was intended to retire in 2025,” Pascucci testified. Does the repair change either Hayden unit’s retirement date?

## The outage list

During the Nov. 5 hearing, commissioners asked Xcel for the 15 days with the lowest operating margin since Jan. 1, 2025\. Xcel’s Nov. 20 filing lists 18, adding what it called “additional representative days beyond the top 15.” For each day, it lists the generating units that were out or derated.

A Hayden unit appears on 17 of the 18 days. Unit 1 accounts for 15 of them. Unit 2 appears on four: Dec. 3, 2025, and July 20, July 26 and Aug. 11, 2026.

Hayden’s units were never the only ones listed. Each of those 17 days names at least six other units out or derated. On Dec. 3, 2025, both Hayden units were among 13 listed, and about 1,200 MW of imports were scheduled to keep the system reliable.

## The decision

The commission kept one evidentiary hearing day, Nov. 5, to “ask questions regarding the unopposed Settlement Agreement.” Did commissioners ask about Hayden that day?

In July, Xcel filed a consensus schedule asking for a decision at the commissioners’ Dec. 2 weekly meeting. In August the commission extended its legal deadline by 130 days and said it would “strive” to rule before Dec. 31.

The Independent is asking Xcel, the commission, the Town of Hayden and Salt River Project for comment and will update this story with any response.

The weekly meetings are held remotely and webcast. The commission’s next weekly meeting is Dec. 2, and it says agendas can change until the day of the meeting.

*The Independent counted the units listed on each day of Xcel’s Nov. 20 list, Hearing Exhibit 118, for the Hayden day counts, the 13 units on Dec. 3, 2025, and the six-unit minimum.*

## Sources

- [Settlement agreement, Hearing Exhibit 111](https://www.dora.state.co.us/pls/efi/EFI.Show%5FFiling?p%5Fsession%5Fid=&p%5Ffil=G%5F837978&ref=yvindy.com), Sept. 28, 2026
- [Hagos and Pascucci direct testimony, Hearing Exhibits 101 and 102](https://www.dora.state.co.us/pls/efi/EFI.Show%5FFiling?p%5Fsession%5Fid=&p%5Ffil=G%5F834883&ref=yvindy.com), June 15, 2026
- [Staff settlement testimony of Erin T. O’Neill, Hearing Exhibit 1400](https://www.dora.state.co.us/pls/efi/EFI.Show%5FFiling?p%5Fsession%5Fid=&p%5Ffil=G%5F838405&ref=yvindy.com), Oct. 13, 2026
- [Supplemental information and Capacity Margin Narrative, Hearing Exhibit 118](https://www.dora.state.co.us/pls/efi/EFI.Show%5FFiling?p%5Fsession%5Fid=&p%5Ffil=G%5F839241&ref=yvindy.com), Nov. 20, 2026
- [Decision C26-0478-I](https://www.dora.state.co.us/pls/efi/EFI%5FSearch%5FUI.Show%5FDecision?p%5Fdec=33030&p%5Fsession%5Fid=&ref=yvindy.com), July 17, 2026
- [Decision C26-0501-I](https://www.dora.state.co.us/pls/efi/EFI%5FSearch%5FUI.Show%5FDecision?p%5Fdec=33054&p%5Fsession%5Fid=&ref=yvindy.com), Aug. 3, 2026
- [Decision C26-0687-I](https://www.dora.state.co.us/pls/efi/EFI%5FSearch%5FUI.Show%5FDecision?p%5Fdec=33251&p%5Fsession%5Fid=&ref=yvindy.com), Oct. 23, 2026
- [Proceeding 26A-0235E docket](https://www.dora.state.co.us/pls/efi/EFI.Show%5FDocket?p%5Fsession%5Fid=&p%5Fdocket%5Fid=26A-0235E&ref=yvindy.com), opened June 15, 2026
- [Commissioners’ Weekly Meeting agenda](https://www.dora.state.co.us/pls/efi/EFI%5FAgenda%5FUI.This%5FWeeks%5FAgenda?ref=yvindy.com), Dec. 2, 2026